Installer: Prime Solar Solutions
Date: 8th January 2026
Equipment Installed:
- 2 x HANCHU 36kW C&I Three Phase Hybrid Inverter
- 6 x HANCHU 9.4kWh High Voltage Batteries
- 208 x 470W solar panels
A solar PV and battery storage system was installed at this commercial office block, enabling the complete removal of the existing gas boiler and transitioning the site to fully electric operation.
Designed to deliver long-term performance and efficiency, the system generates approximately 74,077 kWh annually, contributing to estimated savings of £26,787 per year and £969,395 over its lifetime, with a projected payback period of under 3.5 years.
The system is already performing strongly in real-world conditions – even on overcast days, it is capable of supporting the office block entirely on-site, with battery storage still sitting at 37% capacity, highlighting the strength and reliability of the overall system design.
Visit Prime Solar Solutions website here.